To determine the stability of the three-phase AC charging pile control board, the following aspects can be tested and evaluated:
1. Input voltage range test
Using an adjustable power supply, gradually change the input voltage within the specified range of the charging station control board, check whether the control board can work normally, whether the output current and voltage are stable, and whether there will be abnormal alarms or faults.
2. Big data analysis and monitoring
Data collection: During long-term testing, collect various operational data of the system, including charging current, voltage, power, temperature, charging time, fault records, and other detailed information.
Data analysis: Using data analysis tools and algorithms, analyze a large amount of collected data, observe the trend of data changes, frequency of outliers, failure modes, etc.
Performance evaluation index setting: Establish a performance evaluation index system to measure the long-term stability of the system, such as charging success rate, mean time between failures, data accuracy, etc.
3. Hardware durability testing
Component aging test: Conduct accelerated aging tests on key components on the control board, such as capacitors, resistors, chips, etc., to simulate the aging situation of the components after long-term use.
Mechanical durability test: Simulate the frequent insertion and removal actions of the charging gun, and check whether the interface will have problems such as looseness and poor contact; Perform vibration testing on the control board using a vibration table to check for any issues such as virtual soldering or detachment of components.
4. Software reliability testing
Software update testing: Regularly update the software of the control board, simulate the software upgrade situation in actual use, and check whether the software can run normally after the update.
Abnormal situation handling test: By injecting software exceptions such as data conflicts, communication interruptions, memory leaks, etc., check whether the system's software can handle these abnormal situations correctly.
5. Electrical safety testing
Conduct insulation resistance tests, withstand voltage tests, leakage current tests, etc. to ensure that the charging station meets electrical safety standards.
6. Environmental adaptability testing
Conduct environmental tests such as high temperature, low temperature, humidity, vibration, and impact to verify the reliability and stability of the charging station under different environmental conditions.
7. Electromagnetic compatibility testing
Conduct tests on electrostatic discharge immunity, radio frequency electromagnetic field radiation immunity, electrical fast transient pulse group immunity, surge (impact) immunity, etc., to ensure that the charging station can operate stably in complex electromagnetic environments.
8. Functional testing
Leakage detection function: Test whether the leakage detection function of the control board is normal, such as whether the leakage sensor can accurately detect the leakage situation.
Temperature detection function: Test the temperature detection function of the control board to ensure timely measures can be taken in case of abnormal temperature.
Grounding detection function: Test the grounding detection function of the control board to ensure that the grounding status can be accurately detected.
9. Communication function test
Test the communication function of the control board, including 4G, Ethernet, RS485 and other communication interfaces, to ensure the stability and reliability of communication.
The three-phase AC charging pile control board of Xincheng Technology can comprehensively judge the stability of the three-phase AC charging pile control board through the above tests and evaluations, ensuring its reliability and safety under various conditions. Welcome to inquire and purchase!
Contact:SHEN ZHEN X-CHENG Technology Co.,Ltd